Planning / APSPasses all 6 Full MRP testsProprietary SaaS✓ Verified

Demand forecasting and purchasing for Shopify brands, with a paid Raw Materials add-on that adds bills of materials, production orders and raw-material buying suggestions with a best order date.

Why it is classified this way

We call this a Planning / APS product. A forecasting, constraint-planning, or scheduling engine that normally sits on top of another system that holds your transactions.

This product meets our Full MRP tests, but we classify it by its center of gravity rather than its planning engine alone. The capability table below shows the detail.

The six Full MRP tests, and how Prediko does on each (6 of 6)
  1. YesIt represents a bill of materials, recipe, or formula.Evidence: help.prediko.io › How many raw materials should i order(opens in a new tab); prediko.io › Raw materials management(opens in a new tab)
  2. YesIt accepts dated demand, sales orders, a forecast, or a master production schedule.Evidence: help.prediko.io › Supply plan metrics how the supply plan works(opens in a new tab)
  3. YesIt nets that demand against stock on hand and orders already incoming.Evidence: help.prediko.io › How many raw materials should i order(opens in a new tab); help.prediko.io › How are the buying recommendations calculated(opens in a new tab); help.prediko.io › Supply plan metrics how the supply plan works(opens in a new tab); help.prediko.io › Production orders create a po for missing raw materials i…(opens in a new tab)
  4. YesIt explodes requirements through at least one level of the bill of materials.Evidence: help.prediko.io › How many raw materials should i order(opens in a new tab)The raw-material recommendation explodes finished-goods demand through the BOM: "Analyze BOM: Identify all the finished goods that require the raw material" and "Calculate Demand: Sum the required raw materials during the stock cover period", with a worked example (FG1 needs 500, FG2 needs 250, so order 750). Scope: one level, raw materials under finished goods, on the Raw Materials add-on.
  5. YesIt uses lead times or required dates.Evidence: help.prediko.io › How many raw materials should i order(opens in a new tab); help.prediko.io › How are the buying recommendations calculated(opens in a new tab)
  6. YesIt produces dated buy, make, transfer, release, or reschedule recommendations.Evidence: help.prediko.io › How many raw materials should i order(opens in a new tab)

These rules are applied identically to every product and enforced at build time, a record cannot be published as Full MRP unless all six pass with a source attached. Read the methodology.

Best for

  • Shopify brands that make some of their own products and want raw-material buying driven by the sales forecast
  • Teams that plan purchasing in months and want a best order date per material
  • Growing stores that want unlimited users and SKUs without per-seat pricing

Not a fit when

  • Anyone not selling on Shopify: the app is built on Shopify and billed through it
  • Shops that need routings, capacity scheduling, lots or quality checks, none of which we found documented
  • Larger brands on a tight budget: the price climbs with GMV, to $999 a month from $10M

Pricing facts

What it costs to do manufacturing in this product.

Advertised from

$49/month

Useful entry price

$69/month

Billing basis

Usage-based

Why the useful price is higher

Bills of materials, production orders and raw-material planning are the Raw Materials add-on, $20 a month on top of the $49 app price in the smallest band (under $100K GMV in the last 12 months). Both rise with GMV: $119 + $49 from $100K, $199 + $79 from $500K, $349 + $119 from $2M, and so on to $3,999 + $1,349 below $50M, then contact sales.

Free trial: 14 days.

What moves the real bill

  • Required add-ons. The manufacturing capability needs: Raw Materials Forecasting & BOMs (from $20/mo, rising with GMV).
  • Usage-based. The bill moves with your order, SKU, or transaction volume.

Plans

PlanPriceAdd-ons and setup
GMV under $100KBilled monthly$49/moRaw Materials Forecasting & BOMs $20/mo
Stores with under $100K GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Billed through Shopify Billing. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV under $100KBilled yearly, shown per month$42/moRaw Materials Forecasting & BOMs $17/mo
Stores with under $100K GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Annual plans are "2 months free"; shown per month. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $100K to $500KBilled monthly$119/moRaw Materials Forecasting & BOMs $49/mo
Stores with $100K to $500K GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Billed through Shopify Billing. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $100K to $500KBilled yearly, shown per month$101/moRaw Materials Forecasting & BOMs $42/mo
Stores with $100K to $500K GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Annual plans are "2 months free"; shown per month. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $500K to $2MBilled monthly$199/moRaw Materials Forecasting & BOMs $79/mo
Stores with $500K to $2M GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Billed through Shopify Billing. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $500K to $2MBilled yearly, shown per month$169/moRaw Materials Forecasting & BOMs $67/mo
Stores with $500K to $2M GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Annual plans are "2 months free"; shown per month. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $2M to $5MBilled monthly$349/moRaw Materials Forecasting & BOMs $119/mo
Stores with $2M to $5M GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Billed through Shopify Billing. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $2M to $5MBilled yearly, shown per month$297/moRaw Materials Forecasting & BOMs $101/mo
Stores with $2M to $5M GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Annual plans are "2 months free"; shown per month. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $5M to $10MBilled monthly$499/moRaw Materials Forecasting & BOMs $169/mo
Stores with $5M to $10M GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Billed through Shopify Billing. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.
GMV $5M to $10MBilled yearly, shown per month$424/moRaw Materials Forecasting & BOMs $144/mo
Stores with $5M to $10M GMV in the last 12 months. Unlimited users, SKUs and POs. Shopify stores only. Annual plans are "2 months free"; shown per month. Priced by your store's GMV over the last 12 months, so this plan fits only if your GMV is in its band.

Cheapest paid plan that manufactures, by paid users

  • 1 user: GMV under $100K + Raw Materials Forecasting & BOMs, at least $59 a month (billed yearly, shown per month); first year at least $708.
  • 5 users: GMV under $100K + Raw Materials Forecasting & BOMs, at least $59 a month (billed yearly, shown per month); first year at least $708.
  • 10 users: GMV under $100K + Raw Materials Forecasting & BOMs, at least $59 a month (billed yearly, shown per month); first year at least $708.

Price it for your own users, orders and locations

Pricing detail

The price is set by the store's GMV: "<$100k GMV in the last 12 months" is "$49/month", with "Unlimited Users, SKUs, POs". The pricing page's script lists 13 bands; monthly app prices are $49, $119, $199, $349, $499, $999, $1,499, $1,999, $2,499, $2,999, $3,499 and $3,999, then contact sales from $50M. The Raw Materials add-on ("Raw Materials Forecasting & BOMs") is $20, $49, $79, $119, $169, $349, $499, $649, $799, $999, $1,199 and $1,349 across the same bands; the help center says "This is an Add-on and plan starts from $20 per month." Annual plans are "2 months free" ($42 + $17 in the first band). The FAQ says "We bill customers monthly through Shopify Billing." 14-day free trial; monthly plans from $5M GMV hide the trial badge.

Checked on October 9, 2026. Source: prediko.io(opens in a new tab). Prices change. Check before you buy.

Manufacturing capability

14 of 25 fields resolved. "Unknown" means we have not found first-party evidence. It is not a No.

Planning

Working out what to buy or make, and when.

Planning capabilities, with our finding and its source for each.
CapabilityFindingWhat we found
Accepts dated demandYou can tell it what is due and when, sales orders with dates, a forecast, or a production schedule.YesThe plan is a dated sales forecast: "We look at expected sales day by day, then roll them up into monthly or weekly totals."Reviewed October 9, 2026. Source: help.prediko.io › Supply plan metrics how the supply plan works(opens in a new tab)Question this
Nets against stock on handIt subtracts what you already have before telling you to buy more.YesStock is netted from the recommendation: "If there's existing stock, it will be deducted from this recommendation." For finished goods the Buy table does the same.Reviewed October 9, 2026. Source: help.prediko.io › How many raw materials should i order(opens in a new tab); help.prediko.io › How are the buying recommendations calculated(opens in a new tab)Question this
Counts incoming ordersIt knows about purchase orders and production orders already placed, so it does not tell you to order twice.YesThe Supply Plan asks "What inventory is already coming (confirmed purchase orders)?", and missing raw materials are counted against units in 'Stock' or 'In Transit'.Reviewed October 9, 2026. Source: help.prediko.io › Supply plan metrics how the supply plan works(opens in a new tab); help.prediko.io › Production orders create a po for missing raw materials i…(opens in a new tab)Question this
Uses lead timesIt works backwards from when you need something to when you must order or start it, using supplier and production lead times.YesRaw-material suggestions "Consider Lead Time: Ensure you place orders early enough to meet the stock cover demand", and the finished-goods Buy table works out stock cover after the lead time.Reviewed October 9, 2026. Source: help.prediko.io › How many raw materials should i order(opens in a new tab); help.prediko.io › How are the buying recommendations calculated(opens in a new tab)Question this
Produces dated buy/make suggestionsThe output is an actionable list with dates, order this much by this date, start this batch on this date.YesRaw materials get "To Buy (now)" and a "Best Order Date": "Deadline to purchase SKU to not be below Safety Stock at next potential delivery." Needs the Raw Materials add-on.Reviewed October 9, 2026. Source: help.prediko.io › How many raw materials should i order(opens in a new tab)Question this
Capacity planningChecks whether your people and machines can do the work in the time available.UnknownNot yet researched. We would need: documentation of work-center or resource capacity being compared against load.Know the answer?

Production

Recipes, bills of materials, and running the work.

Production capabilities, with our finding and its source for each.
CapabilityFindingWhat we found
Bill of materialsA list of the parts and quantities needed to make one of something.Yes"Prediko supports Bills of Materials (BOMs), allowing you to link finished goods to their underlying components." Part of the Raw Materials add-on.Reviewed October 9, 2026. Source: help.prediko.io › How many raw materials should i order(opens in a new tab); prediko.io › Raw materials management(opens in a new tab)Question this
Multi-level BOMSub-assemblies inside assemblies, a part that is itself made from other parts, nested as deep as you need.PartialA BOM can include finished goods as well as raw materials, and demand from the BOM is added to that finished good's "To Buy". Nested BOMs several levels deep are not described.Reviewed October 9, 2026. Source: help.prediko.io › Bills of materials bom made from finished goods(opens in a new tab)Question this
Recipes & formulasBatch-style production by weight, volume, or percentage, including scaling a batch up or down.UnknownNot yet researched. We would need: documentation of recipe or formula records, ideally with batch scaling.Know the answer?
Work / manufacturing ordersA record authorising and tracking the making of a specific quantity.Yes"Production Orders are automatically created when any SKU with a Bill of Materials (BOM) is included in the order." Raw materials move to In Production when the order is Ordered and are used up when it is Closed.Reviewed October 9, 2026. Source: help.prediko.io › How to create a production order(opens in a new tab)Question this
Routings & operationsThe ordered steps a product goes through, and which machine or station does each one.UnknownNot yet researched. We would need: documentation of operation sequences or routings attached to production.Know the answer?
Shop-floor trackingOperators report progress, time, and completions as the work happens.UnknownNot yet researched. We would need: documentation of a shop-floor, operator, or terminal interface for reporting production.Know the answer?
Quality controlsChecks, tests, holds, and non-conformance records tied to production or receiving.UnknownNot yet researched. We would need: documentation of quality inspections, checks, or non-conformance handling.Know the answer?

Inventory & traceability

Knowing what you hold and being able to trace it.

Inventory & traceability capabilities, with our finding and its source for each.
CapabilityFindingWhat we found
Batch & lot traceabilityWhich incoming material lots went into which finished batch, and where those finished goods went.UnknownNot yet researched. We would need: documentation of lot or batch numbers tracked through consumption into finished goods.Know the answer?
Expiry & shelf lifeBest-before dates on materials and finished goods, with warnings before they lapse.UnknownNot yet researched. We would need: documentation of expiry, best-before, or shelf-life date fields.Know the answer?
Serial numbersUnique identifiers on individual units, for warranty or field service.UnknownNot yet researched. We would need: documentation of serial number tracking on individual units.Know the answer?

Commerce & accounting

Costs, purchasing, storefronts, and the books.

Commerce & accounting capabilities, with our finding and its source for each.
CapabilityFindingWhat we found
Product costing & COGSWhat it costs you to make one, and the cost of the goods you sold.PartialReceived unit costs from POs can be pushed to Shopify, and POs carry additional costs. We found no manufactured-cost or COGS calculation.Reviewed October 9, 2026. Source: help.prediko.io › Shopify sync automatically push received units and unit c…(opens in a new tab)Question this
PurchasingRaising and tracking purchase orders to suppliers from inside the system.YesPurchase orders are created from the Buy table, and one click makes a raw-material PO for everything a production order is missing.Reviewed October 9, 2026. Source: help.prediko.io › Production orders create a po for missing raw materials i…(opens in a new tab); help.prediko.io › How to create a production order(opens in a new tab)Question this
Accounting connectionSends financial data to bookkeeping software, or includes its own general ledger.PartialXero and QuickBooks are listed under Accounting & Finance on the integrations page. What they sync is not described on the pages we read.Reviewed October 9, 2026. Source: prediko.io › Integrations(opens in a new tab)Question this
Ecommerce connectionPulls orders and pushes stock levels to a storefront or marketplace.YesBuilt on Shopify ("We integrate with Shopify stores on Basic, Advanced and Plus plans"), and the integrations page lists Amazon and TikTok Shop.Reviewed October 9, 2026. Source: prediko.io › Pricing(opens in a new tab); prediko.io › Integrations(opens in a new tab)Question this

Openness & your data

Getting data in, out, and away if you leave.

Openness & your data capabilities, with our finding and its source for each.
CapabilityFindingWhat we found
APIA documented programming interface so other software can read and write your data.YesPublic API reference: "Manage purchase orders - Create, update, and track your POs programmatically" and "Access SKU inventory data - Get stock levels, days left, and buying recommendations".Reviewed October 9, 2026. Source: api.prediko.io › Docs(opens in a new tab)Question this
WebhooksThe system can notify other software the moment something changes.UnknownNot yet researched. We would need: documentation of outbound webhooks or event subscriptions.Know the answer?
MCP supportA Model Context Protocol server, letting an AI assistant read or act on this data. Useful, but it has nothing to do with whether the product plans materials.UnknownNot yet researched. We would need: a first-party mcp server, or documentation of one.Know the answer?
CSV exportYou can get your lists out as spreadsheet files.YesReports export as Excel files ("You can export the report as an Excel file"), and a PO exports as PDF or Excel.Reviewed October 9, 2026. Source: help.prediko.io › Reports(opens in a new tab); help.prediko.io › How to export a po from prediko(opens in a new tab)Question this
Full data exportYou can take everything, including history and relationships, not just a few screens' worth of rows.UnknownNot yet researched. We would need: documentation of a complete account export, database dump, or equivalent.Know the answer?

Deployment, licensing and your data

Deployment
Cloud (hosted for you)
Licensing
Proprietary SaaS
Team sizes
Just me, 2–5 people, 6–20 people, 21–50 people
Manufacturing styles
Kits & bundles, Countable assembled products

Integrations

  • Shopify
  • Amazon
  • TikTok Shop
  • ShipHero
  • Extensiv
  • Xero
  • QuickBooks

Industries

Jobs this product qualifies for

Derived from the capability table above, not hand-assigned.

Editorial notes and cautions

Things we would want a friend to know before buying.

  • The planning evidence is for the Raw Materials add-on. Without it, Prediko plans finished goods only and has no bills of materials or production orders.
  • Price is set by GMV, not users. Check which band your store falls in before comparing: the add-on alone is $169 a month in the $5M to $10M band.
  • Prediko is a planning layer over Shopify, so the store stays the system that holds orders and stock.

Evidence and verification

✓ VerifiedLast checked October 9, 2026 · 56% of capability fields resolved · 100% of those carry a source

Researched 2026-09-19 from the pricing page (its price table was read from the page's own script), the help center and the public API reference. The planning tests rest on the help center's raw-materials and supply-plan articles, which describe the calculation step by step.

Sources we checked (7)

What we still want to confirm

We publish our gaps rather than hiding them. If you can point us at a first-party page for any of these, we will update the record and credit the correction.

  • Check whether raw-material recommendations count open raw-material POs (the Supply Plan article says confirmed POs count; the raw-materials article only mentions stock).
  • Document lot, batch and expiry handling, if any.
  • Find out what the Xero and QuickBooks integrations sync.
  • Check for webhooks and a full data export.

Still unknown: capacity planning, recipes & formulas, routings & operations, shop-floor tracking, quality controls, batch & lot traceability, expiry & shelf life, serial numbers, webhooks, mcp support, full data export.